PHOTOS: Belgrade Airport construction update
NEWS FLASH
Belgrade Nikola Tesla Airport’s expansion project is continuing to advance with the bulk of the work taking place on the new central processor building and the expansion of the A gates area, with an additional floor under construction.
The central processor, currently under development, will stretch over 15.000 square metres and includes the construction of a viaduct for pedestrians and cars, as well as the expansion of the smaller short-term car park which will be located in front of the terminal. The new central processor will enable the airport to boast 100 check-in desks, up to 1.200 square metres of additional retail space and an expanded arrivals area. The project will also allow for faster access and more efficient traffic flow. “The complete reconfiguration, upgrade and improvement of the access road system will enable faster entry and more efficient traffic flow and will increase capacity for short-term and long-term parking. Parking lots will be equipped with a LED lighting system and chargers for electric vehicles. There will also be “Premium parking spaces” available and additional parking spaces for passengers with reduced mobility. This will significantly improve the quality of service, comfort, and accessibility. The works are being undertaken in phases, and we expect for landside contact car parks and access roads to be completed before the next summer season in 2023”, Belgrade Airport’s General Manager, Francois Berisot, said. He added, “The reconstruction and extension phases will bring a brand-new commercial plaza in the central terminal building and additional space for the introduction of various content. This will materialise in the course of 2023”.
Central processor, access road and car parks
Asphalt is being layered on the final segment of the airport’s new 3.500-metre-long inserted runway. Simultaneously, a new lighting system for the inserted runway, which will replace the existing one during its reconstruction, is currently taking place. “Regarding the inserted runway, final works are in progress, and it is expected to be completed at the end of 2022 and put into operation in Q1 of 2023, while reconstruction of the existing runway is to be completed by the end of 2023. Once that is done, the inserted runway will remain in use as a parallel taxiway, and it will contribute to the increase of airport operational capacities”, Mr Berisot explained.
Work is continuing inside the terminal buildings as well, with gates A5 to A10 currently under reconstruction. A new floor is being added above these gates. In addition, work is also taking place at the C5 and C6 gates, which includes the construction of pier that will connect them to the new floor.
A gates
— beg.aero (@AeroNikolaTesla) October 6, 2022
C gates
Other projects are also ongoing, including the construction of the helicopter hangar, the expansion of the de-icing platform and improvements inside the terminal buildings.