PHOTOS: Ljubljana Airport construction update
NEWS FLASH
The construction of Ljubljana Jože Pučnik’s Arport new terminal building is progressing on schedule with the majority of the structure completed. According to operator Fraport, most of the work is now taking place inside the new facility. Equipment such as the security system, lighting and computer equipment is now being installed. The baggage handling system, scanners and escalators have already been put in place in order for Operational Readiness and Airport Transfer (ORAT) exercises to begin at the end of March. Training for the new facility is expected to begin as early as this month. The new terminal, which stretches over 10.000 square metres and features a new departures hall with 22 check-in counters, five security lanes and three baggage carousels, is expected to open in July.